Import Order (New Project)
When importing a new project to Dash360, a specific import order needs to be followed. If you have imported a new system to Dash360, the import order is almost exactly the same. The order is as follows:
- WBS Codes
- Rates Files
- Resource Files
- Resource Results
- Resource Calculations
- Work Package Codes
- Assign Codes to Project (Not an import)
- Cost Estimates
- Resource Assignments
This is the base requirement of data needed to create a functioning project in Dash360.